Board Meeting PowerPoint Presentation
- Project Removal from Capital Pipeline
| District | School | Invitation Date |
| Ipswich | Winthrop Elementary School | June 4, 2014 |
| Tisbury | Tisbury Elementary School | January 27, 2016 |
- Project Removal from Accelerated Repair Program
| District | School | Invitation Date |
| Grafton | North Street Elementary School | May 12, 2017 |
| District | School |
| Blackstone-Millville Regional School District | Millville Elementary School |
| Boston | James Otis Elementary School |
| John D. O’Bryant School of Mathematics and Science | |
| Muriel S. Snowden International School at Copley | |
| Josiah Quincy Elementary School | |
| Rafael Hernández K-8 School | |
| Donald McKay K-8 School | |
| Patrick Lyndon K-8 School | |
| Bourne | Bourne High School |
| Cambridge | Graham and Parks School |
| Danvers | Highlands Elementary School |
| East Longmeadow | Meadow Brook Elementary School |
| Fall River | Westall Elementary School |
| Resiliency Preparatory Academy | |
| Lynn | Lynn Vocational Technical Institute |
| Nashoba Valley Technical School District | Nashoba Valley Technical High School |
| New Bedford | John A. Parker Elementary School |
| Trinity Day Academy | |
| New Salem-Wendell Regional School District | Swift River School |
| Newton | F.A. Day Middle School |
| Bigelow Middle School | |
| Norfolk | H. Olive Day School |
| Norfolk County Agricultural School District | Norfolk County Agricultural High School |
| Quaboag Regional School District | West Brookfield Elementary School |
| Springfield | Milton Bradley School |
| Springfield High School of Science and Technology | |
| Swansea | Joseph Case High School |
| Tantasqua Regional School District | Tantasqua Regional Junior High School |
| Taunton | Taunton Alternative High School |
| Ware | Ware Middle School |
| Stanley M. Koziol Elementary School | |
| West Bridgewater | Howard Elementary School |
| Westborough | Elsie A. Hastings Elementary School |
| Worcester | Challenge and Reach Academy |
- Authorization to Execute Project Funding Agreement - Accelerated Repair Program, Estimated Maximum Total Facilities Grants of $21,007,376
| District | School | Scope | Total Project Budget | Estimated Maximum Total Facilities Grant |
|
John F. Kennedy Elementary School |
Partial Windows/Doors; Boiler | $4,611,588 | $2,526,933 | |
| Boston |
John Marshall Elementary School |
Windows/Doors | $5,429,304 | $3,195,004 |
| East Bridgewater |
Central Elementary School |
Boiler | $1,540,910 | $829,054 |
| Fall River |
James Tasney Elementary School |
Windows/Doors; Partial Boiler |
$2,970,496 | $2,010,223 |
| Samuel Watson Elementary School | Roof; Windows/Doors; Partial Boiler | $10,202,644 | $4,011,560 | |
| Lawrence |
School for Exceptional Studies |
Roof | $4,500,000 | $3,134,072 |
| Mansfield | Mansfield High School | Partial Windows/Doors | $1,880,090 | $861,077 |
| Norton |
Henri A. Yelle Elementary School |
Windows/Doors | $3,901,303 | $2,070,041 |
|
J.C. Solmonese Elementary School |
Windows/Doors | $2,363,618 | $1,243,728 | |
|
L.G. Nourse Elementary School |
Windows/Doors | $2,146,006 | $1,125,684 | |
| Totals | $39,545,959 | $21,007,376 | ||
- Recommendation for Preferred Schematic Design
| District | School | Scope | Estimated Total Construction | Estimated Total Project Costs |
| Belmont | Belmont High School | Add/Reno | $237,594,715 | $295,824,264 |
| Dennis-Yarmouth Regional School District | Mattacheese Middle School | New | $87,140,216 | $112,859,471 |
| Framingham | Fuller Middle School | New | $86,977,969 | $110,556,454 |
| Lowell | Lowell High School | Add/Reno | $270,456,023 | $345,399,220 |
| Shrewsbury |
Beal Early Childhood Center |
New | $74,969,051 | $94,440,597 |
| Wareham |
Minot Forest Elementary School |
New | $71,286,227 | $90,254,704 |
| Totals | $828,424,201 | $1,049,334,710 | ||
- Invitation to Project Scope and Budget - Estimated Maximum Total Facilities Grants of $97,471,381
| District | School | Scope | Total Project Budget | Estimated Maximum Total Facilities Grant |
| Bristol County Agricultural Regional School District |
Bristol County Agricultural High School |
Add/Reno | $103,750,000 | $51,428,124 |
| Northbridge | W. Edward Balmer Elementary School | New | $100,968,194 | $46,043,257 |
| Totals | $204,718,194 | $97,471,381 | ||
AUDIT
- Audit Status Report
- Approval of Final Audits with no appeals, New Program MSBA grants of $39,252,545
| District | School | Scope | Total Project Budget | Total Facilities Grant |
| Andover | Bancroft Elementary School | New Construction | $50,299,859 | $15,837,200 |
| Brockton | Barret Russell Elementary School | Accelerated Repair - Windows and Doors | $2,029,821 | $1,105,363 |
| Clarksburg | Clarksburg Elementary School | Feasability Study | $295,000 | $176,899 |
| Falmouth | Lawrence Middle School | Accelerated Repair - Windows and Doors | $3,947,636 | $1,197,756 |
| Leominster | Johnny Appleseed Elementary School | Accelerated Repair - Roof, Windows & Doors | $3,878,682 | $1,319,043 |
| Southwick-Tolland-Granville | Southwick-Tolland Regional High School | Addition/Renovation | $36,032,893 | $19,616,284 |
| Totals | $96,483,891 | $39,252,545 | ||
MSBA UPDATES
- Executive Director Report
- Project Status