Board Meeting Power Point Presentation
PROJECT
Project Removal from Eligibility Period
District | School | Invitation Date |
Orange | Dexter Park School | March 26, 2014 |
Project Removal from Accelerated Repair Program
District | School | Invitation Date |
Hampden-Wilbraham Regional School District | Wilbraham Middle School | June 4, 2014 |
- Amendment to Feasibility Study Agreement
District | School |
Hopkinton | Center Elementary School |
Narragansett Regional School District | Templeton Center Elementary School |
District | School |
Easthampton | Maple Elementary School |
Everett | George Keverian School |
Lowell | Lowell High School |
District | School |
Ipswich | Winthrop Elementary School |
Millis | Clyde F. Brown Elementary School |
- Authorization to Execute Project Funding Agreement – Accelerated Repair Program
District | School | Scope | Total Project Budget | Estimated Maximum Total Facilities Grant |
Bellingham | South Elementary School | Roof | $1,373,905 | $596,321 |
Brockton | Barrett Russell School | Partial Window | $2,029,821 | $1,515,344 |
Franklin County Regional Vocational Technical School District |
Franklin County Technical School |
Window/Door | $2,100,882 | $1,467,903 |
Gardner | Elm Street School | Window/Door/Boiler | $4,158,176 | $3,129,130 |
Gill-Montague Regional School District |
Sheffield Elementary School | Partial Window/Door |
$1,116,764 | $780,683 |
Hudson | Mulready Elementary School | Partial Roof | $1,499,558 | $743,043 |
Medfield | Ralph Wheelock Elementary School | Boiler | $551,905 | $179,137 |
Melrose | Herbert Clark Hoover Elementary School |
Window/Door | $1,398,853 | $652,579 |
North Attleborough | Roosevelt Avenue Elementary School |
Boiler | $400,000 | $195,035 |
Peabody | John E. McCarthy Memorial School |
Roof Window/Door |
$4,829,568 | $2,550,054 |
South Shore Regional School District |
South Shore Vocational Technical High School |
Boiler | $663,708 | $337,834 |
Wayland | Claypit Hill School | Window/Door | $1,800,000 | $552,551 |
Totals | $21,923,140 | $12,699,614 |
- Recommendation for Preferred Schematic Design
District | School | Scope | Total Project Budget | Estimated Maximum Total Facilities Grant |
Beverly | Briscoe Middle School | New | $98,189,878 | $121,819,300 |
New Bedford | John Hannigan Elementary School | New | $33,001,000 | $40,400,000 |
Totals | $131,190,878 | $162,219,300 |
- Invitation to Project Scope and Budget
District | School | Scope | Total Project Budget | Estimated Maximum Total Facilities Grant |
Woburn | Wyman Elementary School | New | $33,705,396 | $13,974,154 |
Totals | $33,705,396 | $13,974,154 |
Project Status
AUDIT
District | School | Status | Total Project Budget | Final Total Facilities Grant |
Haverhill | Haverhill High School | Waitlist | $34,223,999 | $22,948,008 |
New Bedford | New Bedford High School | Waitlist | $11,412,295 | $7,767,018 |
Totals | $45,636,294 | $30,715,026 |
District | School | Scope | Total Project Budget | Total Facilities Grant |
Berkshire Hills Regional School District | Monument Mountain Regional High School | FSA | $750,000 | $351,194 |
Fairhaven | Rogers/Leroy Wood Elementary School | New | $23,577,607 | $13,062,017 |
Marlborough | Marlborough High School | Green Repair | $7,048,596 | $3,092,286 |
Francis J. Kane Elementary School | Green Repair | $1,048,677 | $348,666 | |
Narragansett Regional School District | Phillipston Memorial Elementary School | Green Repair | $161,232 | $78,096 |
Southeastern Regional Vocational Technical School District | Southeastern Regional Vocational Technical High School | Add/Reno | $33,677,475 | $25,120,098 |
Springfield | Mary M. Walsh Elementary School | Green Repair | $819,836 | $603,617 |
Milton Bradley Elementary School | Green Repair | $767,533 | $532,064 | |
Totals | $67,850,956 | $43,188,038 |
FINANCE
- 2014 Series A Takeout Issuance Update
- Commercial Paper Program Update
- Sales Tax Collections Update
- Grant Payments Update – Prior Grant, Waiting List, and New Program Payments